The four Four Palms villas under construction in Kedungu, photographed on 22 September 2026

Construction updates · Kedungu, Bali

Four Palms, taking shape

A dated record of the build: project reports, site photographs and how to arrange a visit.

Render and reality

The design, and the building

The architectural render of the front elevation, and the same elevation photographed on site. The render shows the intended finished design; the photograph shows the work on the date in its caption.

Architectural render of the Four Palms front elevation showing the intended finished design
The Four Palms front elevation under construction with the project site board, 22 September 2026

Architectural render. The intended finished design.

Construction log

Every update, newest first

Each entry is dated and names its source, so you can see what was reported, what was photographed and when. New entries are added as the project issues them.

Project update

80% of the development reported complete

The September update, dated 30 September 2026, puts overall construction progress at 80% across the development, with completion and handover targeted for December 2026.

The figure covers the development as a whole. Ask the team to confirm the position for the villa you are considering before you reserve.

80%Overall construction progress reported
Overall progress
80%Position reported by the project
Update date
30 September 2026
Completion target
December 2026
Handover target
December 2026

Site photography

Roofs on, scaffolding still up

The photographs below were taken across the site on 22 September 2026. They show the four villas with their roof structures in place, scaffolding still standing to the front elevation, and the courtyards and pool areas formed.

They are a visual record of that date only. The measured position of the work is in the 30 September update above.

Photographed
22 September 2026
Photographs in this entry
18Taken across the site
Nearest reported position
80%From the 30 September update
Four Palms front elevation under construction, roofs on and scaffolding in place, 22 September 2026
Front elevation with the roofs on.
The Four Palms site board in front of the four villas under construction, 22 September 2026
The site board on the street frontage.
The four Four Palms villas seen from the lane during construction, 22 September 2026
The villas from the lane.
Aerial photograph of the four Four Palms villas under construction, 22 September 2026
All four villas from the air.
Aerial photograph of the Four Palms villas and their roof structures, 22 September 2026
Roof structures across the row.
Aerial photograph of the Four Palms development in Kedungu, 22 September 2026
The development from above.
Courtyard and pool area of the Four Palms villas under construction, 22 September 2026
Courtyard and pool area.
Construction progress at the Four Palms villas in Kedungu, 22 September 2026
Progress across the plot.
Interiors of the Four Palms villas under construction, walls and openings formed, 22 September 2026
Interiors with walls and openings formed.
Two of the Four Palms villas photographed from directly above, 22 September 2026
Two villas from directly above.
Roofs and courtyards of the Four Palms villas, 22 September 2026
Roofs and courtyards.
Roof structure of the Four Palms villas seen from above, 22 September 2026
Roof structure from above.
Scaffolding against the Four Palms villas during construction, 22 September 2026
Scaffolding still in place.
The Four Palms site and the surrounding Kedungu neighbourhood, 22 September 2026
The site in its neighbourhood.
The Four Palms villas and the approach road in Kedungu, 22 September 2026
The villas and the approach road.
The Four Palms site in context among the surrounding houses in Kedungu, 22 September 2026
The site in context.
Aerial photograph of the Four Palms villas with the Kedungu coastline beyond, 22 September 2026
The coastline beyond the village.
Rice fields beside the Four Palms site in Kedungu, 22 September 2026
Rice fields beside the site.

Site photographs taken on 22 September 2026. They show the work on that date and are not a statement of completion. Architectural renders elsewhere on this site show the intended finished design.

Project report

70% of the development reported complete

The project report dated 30 July 2026 puts overall construction progress at 70% across the development, with completion and handover targeted for December 2026.

The figure covers the development as a whole. Ask the team to confirm the position for the villa you are considering before you reserve.

70%Overall construction progress reported
Overall progress
70%Position reported by the project
Report date
30 July 2026
Completion target
December 2026
Handover target
December 2026
Four Palms development masterplan showing the four villas, their pools, the access road, parking and the site boundary
Four Palms development masterplan by 20/10 Architects. Opens full size in a new tab.

Layout

See the homes on site

The plans show how the four villas, private pools, access, parking and service areas are arranged. A visit lets you put that layout into context and see the progress of the homes you are considering.

Architectural renders show the intended finished design. Site photographs show the work at the date in their caption.

Handover

From completion to handover

The project provides for key handover and a 30-day testing period. Its stated warranty commitments are one year for the villa, excluding items with shorter manufacturer warranties, and five years for the structure. The purchase documents set out the scope, start dates and claims procedure.

Before choosing a payment plan, confirm the current completion programme, the handover inspection and how the final signing and lease transfer are arranged.

Approval timetable

The project plans to start the SLF application after construction and has given an estimated processing period of 10 to 12 months, subject to authority review. The timing of lawful occupation or rental needs separate written confirmation. It should not be assumed to match the physical handover date.

Review the approval timetable and its effect on your plans with the team and your independent adviser.

Before purchase

The project plans to begin its SLF process after construction, with an estimated processing period of 10 to 12 months, subject to authority review. Receiving keys alone does not establish the date your intended occupation or rental can lawfully begin.